30.5. Control start procedure

To start testing:
• An operator needs to be logged on with the authorization access level
high enough to perform testing.
Caution:
The Logging on procedure is described in ch. 11. The procedure
of outlining the authorization level is described in ch. 19 of this manual.
• Select a product to be tested with correctly determined data for the
control process,
• Enter to scale memory general parameters on control mode (in
accordance with ch. 30.2 and 30.3 of this manual),
• Remove load from the weighing pan,
• Press function hot-key
of the settings window, which opens an information window on entered
data:
where:
Abort control start
Control start
(control start) located in the bottom bar