38) Installation of Power Unit
Clean power unit mating surface, and install dowel pin 1
1.
and gasket 2.
Install power unit 3, and tighten bolts 4 in two or three
2.
steps to specified torque.
Power Unit Installation Bolt :
30 N·m ( 22 lb·ft ) [ 3.0 kgf·m ]
Install apron 5.
3.
Reconnect breather hose 6, cooling water (fuel cooler) hose
4.
7 and fuel hose 8.
Install oil level gauge 9.
5.
Reconnect throttle link rod 0. For the adjustment procedure,
6.
refer to sections describing adjustment of throttle link and
throttle cable and inspection of gear shift operation in
Chapter 3.
7.
Apply grease to sliding parts such as links and cables.
Install PTT switch coupler, PTT motor leads q and battery
8.
cables w.
Positive Battery Cable Nut :
4 N·m ( 3 lb·ft ) [ 0.4 kgf·m ]
PTT Motor Lead Bolt :
4 N·m ( 3 lb·ft ) [ 0.4 kgf·m ]
25/30 2006
2
1
1
4
4
6
9
3
5
7
5
8
0
q
w
5-57