FC 300 Design Guide
Initial Commissioning
Doing the initial commissioning, the easiest way to go through is using the Quick Menu button and follows
the quick set-up procedure using G-LCP (read table from left to right):
Press
0-01 Language
1-20 Motor power
1-22 Motor voltage
1-23 Motor frequency
1-24 Motor current
1-25 Motor nominal speed
5-12 Terminal 27 Digital In-
put
1-29 Automatic Motor Adap-
tation
3-02 Minimum reference
3-03 Maximum reference
3-41 Ramp1 up time
3-42 Ramp1 down time
3-13 Reference site
114
How to Programme
Q2 Quick Menu
Set language
Set Motor nameplate power
Set Nameplate voltage
Set Nameplate frequency
Set Nameplate current
Set Nameplate speed in RPM
If terminal default is Coast inverse it is pos-
sible to change this setting to No function.
No connection to terminal 27 is then needed
for running AMA
Set desired AMA function. Enable complete
AMA is recommended
Set the minimum speed of the motor shaft
Set the maximum speed of the motor shaft
Set the ramping up time with reference to
nominal motor speed (set in par. 1-25)
Set the ramping down time with reference to
nominal motor speed (set in par. 1-25)
Set the site from where the reference must
work
MG.33.B7.02 - VLT is a registered Danfoss trademark

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the FC 300 and is the answer not in the manual?

Questions and answers

Table of Contents