STEP 5 - Connect Pre-Installed Cabling (Pedestal-to-Head)
Numerous cables are pre-installed within the pedestal and must be routed up to the underside of the projec-
tion head, where they connect to one of three panels (or two IEC power sockets). Connect pedestal-to-head
cabling as follows:
NOTE: For all cable connections, keep cable ties that have been trimmed at manufacture, but remove
temporary ties that are untrimmed and have tails.
a. Open both pedestal doors (Figure 2-5).
b. Open the rear side door on the operator's side.
c.
SET BALLAST AC INPUT SWITCH:
Before connecting the ballast to AC, set the
ballast's AC input switch to match the AC
available at the site. Toggle left for nominal
200 VAC supplies and toggle right for 400
VAC supplies. The factory default is 200 VAC.
d.
BALLAST RS-232 CABLE:
Connect the ballast's RS-232 cable 34-002075
to Panel B (9-pin), routing through the small
rectangular access hole in the front underside
of the projection head (Figure 2-6).
e.
BALLAST INTERLOCK CABLE:
Connect the ballast's interlock cable 34-002007 to Panel C (9-pin), routing through the small rectangu-
lar access hole in the rear underside of the projection head (Figure 2-6). Ensure a second connector
from Panel C to Panel B is connected (P/N 001-100376-01). The remaining third connector is a non-
functional spare.
CP2000-SB User Manual
020-100162-06 Rev. 1 (03-2014)
Figure 2-6 Connect Ballast RS-232 and
Interlocks to Projection Head
Section 1: Introduction
Figure 2-5 Open Projector for Access
2-5

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents