Installation Procedures
553-3021-210
Standard 7.00
Wear the anti-static wrist strap provided in the bottom of the cabinet
before handling the power supplies or other circuit cards. Static
electricity can damage the components of power supplies and circuit
cards.
Procedure 2
New system installation
1
Install the Main Cabinet
a) Mount the cabinets as described in "Mounting the cabinets"
on page 115.
b) Remove the drip tray from each cabinet to expose the cable
routing grooves at the bottom rear of the cabinet.
c) Install the cabinet ground wire for the main cabinet as
described in "Installing the system ground" on page 125.
d) Install the power supply as described in "Installing the power
supplies" on page 131.
e) Install the reserve power supply if required.
Refer to "Installing and connecting reserve power supplies"
on page 199.
f)
Install the System Controller Card and daughterboards. Refer
to "Installing System Controller Cards" on page 143.
g) Install the remaining circuit cards. Refer to "Installing the
circuit cards" on page 187.
h) Install the cross-connect terminal and cables. Refer to
"Installing and connecting cross-connect terminals to
cabinets" on page 169.
i)
Install the power fail transfer units (PFTUs) if provided. Refer
to "Installing power fail transfer units" on page 181.
j)
Connect the SDI and Ethernet interfaces. Refer to "Installing
and connecting SDI and ethernet ports" on page 213