16
Cables
I
For the cable plan see section
16.1
Installing the RAID upgrade kit
Field Replaceable Units (FRU)
Average task duration: 5 minutes
V
CAUTION!
Follow the safety instructions in chapter
page
43.
16.1.1 Required tools
Preliminary and concluding steps: tool-less
●
Main steps: tool-less
●
16.1.2 Preliminary steps
Ê Perform the following procedures:
1.
"Opening the rack door" on page 59
2.
"Locating the defective server" on page 55
3.
"Shutting down the server" on page 59
4.
"Extending/removing the server from the rack" on page 60
5.
"Opening the server" on page 64
RX100 S7
"Cabling" on page
Upgrade and Maintenance Manual
462.
"Important information" on
385