9. Verify the operation of the rack rails:
a. Fully extend the chassis out of the rack.
b. Check that there is enough slack in the cables and cords for full extension of the chassis. Make sure that there is no cable binding or
crimping.
c. To ensure that the cables and cords are secured properly, slide the chassis in and out of the rack. Make sure that there is no risk of
accidental disconnection of the peripheral cables and power cords.
10. Slide the server into the rack until the chassis ears are flushed against the rack posts.
11. (Optional) Open the chassis ear latches, and then tighten the shipping screws.
Results
Results
HPE ProLiant DL325 Gen11 Server User Guide
79