5.5.3. Move the sliding plate of the guidance plates of the cabinet

Preconditions:
Tools: spanner (size 13).
1.
Loosen the bolts (A).
2.
Move the sliding plate (B) of the 2 guidance plates.

5.5.4. Route cables through guidance plates

1.
Route the cables (A) through the right guidance plates (B).
2.
Make sure that there is sufficient cable length to reach the connectors at the top of the
cabinet.