Installation Instructions; About Construction; Instruction For A Wall Bearing; Mounting On A Pedestal - ABB Terra DC Wallbox C UL Installation Manual

Three-phase version
Hide thumbs Also See for Terra DC Wallbox C UL:
Table of Contents

Advertisement

4

Installation instructions

4.1

About construction

The construction phase includes all work required to prepare the location and ensure it is ready for the
placement and connection of the Terra DC Wallbox charger. The construction phase can start when:
The wall preparation work is done.
All necessary permits are granted.
The grid connection is available.
4.2

Instruction for a wall bearing

1.
Drill and tap 4 holes and insert the plug for fixation in the wall at the indicated positions (refer
to technical drawing in the Appendix A par. 10.1). For safety purposes, the number of recom-
mended fixing screws is 4xST7.3x70. This is assuming the appropriate type of wall plugs are
used (depends on wall's characteristics, structure and type). It is the installer's responsibility to
choose an appropriate wall plug and to plan for a load of 820 N on each plug.
2.
When selecting the area along the wall for installation, ensure the required free spaces for the
Terra DC Wallbox cables are available (refer to section 3.4).
4.2.1
The Terra DC Wallbox can also be mounted on a pedestal. In order to achieve a safe installation, the
minimum set of requirements are included in Appendix C – Pedestal requirements). For the ABB pedes-
tal solution, contact your local ABB sales representative.
4.3

Power feed

The power cable enters the charger from below. Use conduit, foam, or proper cable lugs and glands to
prevent animals from entering the AC or Ethernet cable inlets. (Reference Section 3.2 for feeder specifi-
cations)
4.4

Internet connection

The preferred method of communication is the wireless 4G modem integrated into the charger. A cus-
tomer SIM card is not required. A subscription for the SIM card is provided by ABB for select countries.
If there is no wireless signal available, a standard wired internet connection is required. (Reference Sec-
tion 3.1, 3.2.5 and 3.2.6 for wiring and connection methods)
The connection must be available for the ABB service engineer and the NOC (Network Opera-
tion Center).
Please contact ABB (800.825.2556 option 2) for a specific configuration.
If a separate internet connection is not used, please ensure the cable entry hole is closed to retain the
IP54 grade of the cabinet and prevent insects and small animals from entering the cabinet.
20 2 0- 10- 05

Mounting on a pedestal

T ER R A DC WA LL BOX U L
20 / 38

Advertisement

Table of Contents
loading

This manual is also suitable for:

Terra dc wallbox cj ulTerra dc wallbox ul

Table of Contents