Install the CPS6000 Shelf
Important Note
The following procedures are in order for a typical application. If the left side of the shelf will be
blocked after the shelf is installed in the framework, the following procedures should be done before
installing the shelf:
•
Inter-Shelf Connections (multi-shelf installations only)
•
AC Connections
•
Office Alarm Cable
•
Thermal Probe Connection
Leave a sufficient service loop on these cables.
Install the CPS6000 Shelf
Follow the steps in the table below to mount the CPS6000 shelf into a 19-inch or 23-inch frame.
Step
Action
Locate the 2 mounting brackets, one on each side of the CPS shelf; align the holes in the shelf-mounting
1.
bracket with the holes in the mounting frame. See Figure 5-4.
Attach the CPS shelf to the frame using a minimum of four (two on each side) of the 12-24 screws
2.
included in the supplied parts bag. Refer to the table below for Torque Specifications.
Hardware
Metric M5
12-24
Metric M6
Page 40
© Copyright 2021 ABB. All rights reserved.
Nm
4
4
7.3
Figure 5-4: CPS6000 Frame Mounting
Torque
In-lbs.
35
35
65