Install wedge, screw, and washer. Apply Ultra
Lock to threads and torque screw 15 to 20 in. lbs.
(1.7 to 2.3 N·m).
Re-torque two retainer screws to 18 to 20 ft. lbs.
(24 to 27 N·m).
Confirm that torque on the wedge screw is 15 to
20 in. lbs. (1.7 to 2.3 N·m).
To complete gearcase assembly, refer to:
LEAK TEST on p. 308
WATER PUMP on p. 311
SHIFT ROD ADJUSTMENT on p. 314
REMOVAL AND INSTALLATION on p. 308
LUBRICANT on p. 307
Propeller Hardware Installation on p. 74
Trim Tab Adjustment on p. 77
During break-in period of a reassembled gear-
case, change the gearcase lubricant between 10
to 20 hours of operation.
DSM02291
DSC02361
GEARCASE
COUNTER ROTATION