General Instructions; Before Commissioning; Pressure Build-Up In The Overall Supply - Festo VTSA-44-MP Series Manual

Valve terminal
Hide thumbs Also See for VTSA-44-MP Series:
Table of Contents

Advertisement

4. Commissioning
4.1

General instructions

4.1.1 Before commissioning

4.1.2 Pressure build-up in the overall supply

4-4
Switch off the power supply before connecting or discon-
necting plug connectors (otherwise functional damage).
Only commission a valve terminal that has been mounted
and wired completely.
Make sure that there is a sufficient supply of fresh air
(cooling) for the following operating conditions:
– maximum number of valves
– maximum operating voltage
– when the solenoid coils are constantly under stress
Please observe the following instructions on building up
pressure in the overall supply.
Warning
If the build-up of pilot air is too slow or delayed, this may
lead to sudden unexpected movements of the actuators
under the following conditions:
– When the compressed air is switched on via a soft-start
valve
– If there are electric signals (e.g. after EMERGENCY STOP)
This can cause damage to the machine or system and even
injury to persons.
Operate the valve terminal with external pilot air
corresponding to the pressure specified in Appendix A,
Tab. A/6. The pilot air must be branched in front of the
soft-start valve (see diagram).
Festo P.BE-VTSA-44-EN en 1101f