Verifying the Installation

007-4209-003
To verify a successful installation of the DCD, follow these steps:
1.
Open a UNIX shell.
2. At the prompt, enter
A hardware inventory list will appear, similar to the one shown in Figure 3-7.
3. Look for the following line describing the DCD:
DCD
If the above line does not appear, proceed to Chapter 5, "Troubleshooting and
Technical Specifications."
Note: If a DCD is installed in a Silicon Graphics Fuel workstation, or if one or two DCDs
are installed in a Dual Head Octane system, the hardware inventory list will be slightly
different than the Single Head Octane inventory shown in Figure 3-7. However, you
should still look for a line that says "DCD" (or look for two such lines, if you have two
DCDs installed).
Display option
board
Figure 3-7
Hardware Inventory List after Installing the DCD
hinv
winterm
grip# hinv
2 250 MHZ IP30 Processors
CPU: MIPS R10000 Processor Chip Revision: 3.4
FPU: MIPS R10000 Floating Point Chip Revision: 0.0
Main Memory size: 128 Mbytes
Instruction cache size: 32 kbytes
Data cache size: 32 kbytes
Secondary unified instruction/data cache size: 1 Mbyte
Integral SCSI controller 0: Version QL1040B (rev. 2), single ended
Disk drive: unit 1 on SCSI controller 0
Integral SCSI controller 1: Version QL1040B (rev. 2), single ended
IOC3 serial port: tty1
IOC3 serial port: tty2
IOC3 parallel port: plp1
Graphics board: V12
Integral Fast Ethernet: ef0, version 1, pci 2
Iris Audio Processor: version RAD revision 12.0, number 1
Dual Channel Display

Verifying the Installation