UTILITY PACKAGE (SW1DNC-EIPUTL-E)
7.3
Operating Procedure
Start
Check box
Start Utility package.
Create a new project?
Click [File]
[New].
Complete the IP Address setting.
Complete the Common Parameter setting.
Set the following parameters.
Class1 Tag Parameter
Class3/UCMM Tag Parameter
Refresh Parameter
Configure the Transfer Setup settings.
Write the parameters.
Read intelligent function module
parameters in GX Works2.
Monitor the data in the monitoring screen.
End
The following flowchart shows how to create, edit and write a project to the system.
No
Yes
Figure 7.5 Operating Procedure
POINT
The "Transfer Setup" window appears only at the first startup after the installation.
Make settings to connect Utility Package to the CPU module. (
Configuring the EtherNet/IP module)
Check box
Open the existing project.
Section 7.7.1
Yes
Change a project?
Section 7.9.1 (1)
Section 7.9.1 (1)
Section 7.9.2, Section 7.9.3
Section 7.9.4
Section 7.9.7
Section 7.10.1
Yes
Write the parameters
to the module?
Section 7.10.2
Section 7.10.2 (3) (a)
Section 7.6, Section 7.11
7.3 Operating Procedure
Section 7.7.2
No
No
Section 7.10.1