Chapter 1. Commissioning
Typical Commissioning Check Process
Table 1-1.
Step Description
1
Physical installation inspection
2
Antenna alignment confirmation
3
Configuration confirmation
4
Commissioning tests
5
Capturing as-built data
6
Final inspection and sign-off
Vol. V-1-2
A typical commissioning process is summarized in Table 1-1.
Procedure
A physical check prior to antenna alignment and node configuration to
ensure that the physical installation is complete and correct.
An antenna alignment procedure is detailed in Volume II, Chapter 5.
Recorded RSLs should be within 2 dB of calculated RSLs.
A check, using CT, to ensure that Node configurations are complete and
correct and that:
• Links are operating error-free.
• All relevant alarms are extinguished.
• Link performance data is as expected.
• Node/Terminal visibility is provided at the network management
center (where network managed).
Tests designed to confirm correct link operation. Refer to
Commissioning Tests on page 1-3.
Recording all relevant installation and performance data for future
reference. Refer to Commissioning Records on page 1-18.
Completion of 'paperwork' recording installation hand-over for
operational use, and/or any remedial action needed to complete an
installation. Refer to Commissioning Records on page 1-18