Pst Calibration - Fisher FIELDVUEDVC6200f Instruction Manual

Digital valve controller for foundation fieldbus
Table of Contents

Advertisement

DVC6200f Digital Valve Controller
Calibration
February 2017
5. The instrument sets the output pressure to full supply. The following message appears.
Use the Increase and
Decrease selections
until the displayed
pressure matches the
output x pressure.
Press OK when you have read the message.
6. The value of the output pressure appears on the display. Press OK to display the adjustment menu.
7. From the adjustment menu, select the direction and size of adjustment to the displayed value. If the displayed value
does not match the output pressure, press OK, then repeat this step (step 7) to further adjust the displayed value.
When the displayed value matches the output pressure, select Done and go to step 8.
8. Place the transducer block in Auto and verify that the displayed pressure matches the measured output pressure.

PST Calibration

To perform a PST Calibration, place the instrument transducer block in Manual. Follow the prompts on the Field
Communicator display to select the desired Outgoing and Incoming ramp rates, and define the Minimum Travel
Movement. The instrument then performs the PST calibration; when prompted, input the desired behavior on a failed
PST. On completion of PST calibration the configured parameters are presented for verification.
Refer to DVC6200f PST Calibration and Testing using ValveLink Software (D104217X012) for additional PST
configuration and calibration information.