Figure 3-11. Top cover of the 5U control module
|
|
|
|
|
|

Verifying Rack Mount Kit Contents

3-12
TS3310 Tape Library Setup and Operator Guide
3. Remove the top cover from the 5U control module.
4. Ensure that the front and rear gear racks of both the control module and the
expansion module are locked in the upper position (see 2 in Figure 3-19 on
page 3-21).
5. Install the top cover, using the T10 Torx screws.
The Rack Mount Kit will include rails and hardware to install one library module
in a rack. An Additional Rack Hardware Kit with the necessary parts to install an
additional module will be included with each additional module ordered.