AssayMAP Bravo Platform Installation Guide
b
On each side of the open pump head, turn the dial to open the clamps
(V-grooves) fully to accommodate the diameter of the tubing.
Figure Open pump head (side view) with fully open clamp and clamp dial
c
Insert the length of tubing so that it gently arches over the rollers.
Ensure the tubing is located in the center of the tube clamps
(V-grooves) on either side of the pump head, and then carefully lower
the cover.
CAUTION
Ensure that the pump head clamps are set properly for the diameter of the
tubing. Incorrectly adjusted clamps can constrict the flow or damage the tubing when the
pump head is closed.
Note: If any creeping of the tubing occurs during operation, tighten the
clamps slightly using the clamp dials.
4
For the bottom pump:
a
Prepare an approximately 20.32- to 25.4- cm (8- to 10- inch) length of
5/16- inch tubing, and insert a union connector (figure, a) on each end.
b
Connect a 10.16- cm (4- inch) length of 1/4- inch tubing (b) to each of
the union connectors.
c
Connect quick- disconnect fittings (c) to the free end of each 1/4- inch
tubing section.
d
Place this tubing assembly within the bottom pump head. Refer to
step 3 for the detailed procedure.