FINAL DRIVE
8. Install both front axles from the front gearcase.
Ensure the axles are fully seated.
9. Install both front upper control arm from the bearing
carrier. This will allow the lower control arms to be
lowered creating clearance to remove the axles from
the front gearcase.
8.40
10. Install both front upper ball joint fasteners. Torque to
specification.
TORQUE
Front Upper Ball Joint Pinch Fastener:
42 ft-lbs (57 N·m)
11. Install both tie rod ends from the bearing carriers.
Torque to specification.
TORQUE
Tie Rod Retaining Nut:
Step 1: 30 ft-lbs (41 Nm)Step 2: Tighten additional
9850045 R01 - 2020-2021 RANGER 1000 Service Manual