WDMX setup and testing: integration procedures
........................................................................................................................................................................
................................................................................................................................................
6
Click Select and expand the circuit pack list by clicking the "+" next to XM10G/8,
highlight Port 9 OTU-2 and the port will appear on the right side of the screen, click on
the AID to highlight it then click Select.
................................................................................................................................................
7
Click Select for the Add/Drop port, expand the circuit pack (OMD5/8) and click on the
Port (the port must match XM10G/8 OTU-2 port) and the port will appear on the right
side of the screen, click on the AID to highlight it then click Select.
................................................................................................................................................
8
Click Next, then Finish and complete the cross-connection by clicking on Yes in the
confirmation window.
................................................................................................................................................
9
Connect fibers from the LNW705 Port 9 to the corresponding channel on the LNW785
while observing proper optical power levels and cleaning procedures.
................................................................................................................................................
10
Repeat
................................................................................................................................................
11
Connect the Transmit fibers to the OTS port on the LNW785 at each end of the span,
following proper fiber cleaning procedures.
................................................................................................................................................
12
Connect the Receive fibers, while observing optical power requirements and cleaning
procedures
................................................................................................................................................
13
Observe test set and verify error-free transmission. If only one test set is available, connect
a fiber from the In port to the Out port of the PTM in port 1 at one end. Use the
information listed in
LBO/Attenuator.
Note:
customer.
................................................................................................................................................
14
Disconnect test set(s) and fiber jumper from ports.
........................................................................................................................................................................
8 - 1 0
Step 1
though
Step 9
at the remote node.
Table 8-4, "Attenuation Table" (p. 8-19)
Test duration may be determined by engineering specification or by the end
to determine the proper
Alcatel-Lucent 1665 DMXtend R10.0
365-372-327R10.0 Issue 1
January 2013

Advertisement

Table of Contents
loading

Table of Contents