HDD installation
Table 8-145 HDD installation
1.
Slide the replacement HDD and bracket into the guides. Continue to install the HDD and bracket
into the BEP until it seats into the motherboard.
2.
Re-installed the two Phillips screws to secure the HDD and bracket to the BEP frame. Hand
Tighten.
3.
Connect the power and SATA cables to the HDD.
4.
Connect the battery cable to PCN1 on the CB.
5.
Make sure all cables are clear of the BEP Cover and tilt the top of the BEP cover toward the BEP.
Be careful not to pinch any of the cables when installing the BEP cover.
6.
Tighten and secure the thumb screws or screws at the top of the BEP cover, or the three screws
that attach the cover to the BEP.
7.
Replace the side cover.
8.
Power up the system.
9.
Reinstall the Base Load and Application Software.
10. Enter the TCPIP settings and Option strings for the LOGIQ E9.
11. Restore the Patient Archive images, Report Archive, User-Defined Configuration (Customer
Presets), and Service settings.
12. Perform Functional Checks. See:
8-9-7-4 - Verification
. 2
EV
Steps
NOTICE
and
Chapter 8 Replacement procedures
8-9-7-3 - Calibration and
8-9-7-5 "Functional Checks" on page
LOGIQ E9 S
ERVICE
Corresponding Graphic
adjustments,
8-234.
M
ANUAL
8 - 233

Advertisement

Table of Contents
loading

Table of Contents