5.3.16 How to Set and Add a PMAC615 AC Meter?

Prerequisites
One end of the straight-through cable has been connected to the RS485 port on the PMAC615
AC meter, and the other end has been connected to the COM port on the ECC800.
Context
The model of the single-phase AC meter for the lighting control box is PMAC615.
Procedure
Step 1 Set the PMAC615 communications address.
Issue 07 (2020-03-16)
Log in to the ECC800 WebUI as an administrator.
Add a PMAC625.
Parameter
Name
Device attribute
Device Type
Connect To
Communications
Port
Device Address
Click Test Connect to check whether the PMAC625 connects to the ECC800 properly.
If the PMAC625 connects to the ECC800 properly, click Confirm. The connected
devices are displayed in the Number of connected devices list.
If the PMAC625 does not connect to the ECC800 properly, check whether the cable
between the PMAC625 and the ECC800 is connected properly, whether the
PMAC625 and ECC800 are running properly, and whether the input parameters are
consistent with the PMAC625 parameters.
Choose Monitoring > System > ETH Converter Group > ETH Converter n >
Running Parameters and set Device name to ETH Converter n_Device name.
Copyright © Huawei Technologies Co., Ltd.
Setting
Select Electricity Meter from the drop-down list
box.
Select PMAC625 from the drop-down list box.
Select ETH Converter n from the drop-down list
box.
Select COM1/COM2 from the drop-down list box.
In this example, Device Address is set to 100.
During actual configuration, set the device address
for the PMAC625 based on the actual situation.