ECC800 Data Center Controller
User Manual
7.1 NetEco Management
7.1.1 Connecting the Communications Cable
Procedure
Step 1 Connect the communications cable to the WAN_1 port on the ECC800.
Figure 7-1 Connecting the communications cable
----End
7.1.2 Setting NetEco Parameters
When the smart module can be connected to the NetEco, perform the following steps to
configure parameters.
Procedure
Step 1 Apply for a fixed IP address to the equipment room network administrator.
Step 2 Set the IP address, subnet mask, and default gateway on the ECC800 WebUI.
Issue 07 (2020-03-16)
7
Copyright © Huawei Technologies Co., Ltd.
Remote Management
7 Remote Management
170