8.0 SHUT DOWN
8.1 MBR Temporary Shut Down
A temporary shutdown for a few days requires continuous aeration of the biomass to keep the
DO level at least 2 mg/L and continuous biomass recycle between the bioreactors.
8.2 MBR Permanent Shut Down / Winterizing
Permanent shut down is required if system operation stops for at least 2 weeks without inflow.
Permanent shut down includes the following procedure:
8.2.1 Process Shut Down Procedure
Conduct a "Backwash Now" operation on the system
Stop influent flow into the System
Ensure all pumps are in the "OFF" position using the HOA HMI screen
Ensure all Blowers are in the "AUTO" position using the HOA HMI screen. This is to be
done until a vacuum truck can be provided or contracted locally to clean out the tanks.
Ensure all automated valves are in the "OFF" position using the HOA HMI screen.
Ensure that the MBR is disabled using the HMI screen button
Conduct all maintenance procedures on Section 7 Table – regardless of schedule time
8.2.2 Cleaning - General
Conduct general system interior cleaning
Open all tanks, wash out with a garden hose and Vacuum out.
Clean all sensors and level switches
8.2.3 Membranes
Ensure that the membrane tanks (TNK-601/602) are drained before opening the membrane
tanks.
Open TNK-601/602 doors with hand/power tools.
newterra O&M Manual
© 2017 by newterra, ltd.
All rights reserved. No part of this document may be reproduced or transmitted in any form or by any means, electronic, mechanical,
photocopying, recording, or otherwise, without prior written permission of newterra ltd.
1291 California Avenue, Brockville, ON K6V 5W3
(800) 420-4056 / www.newterra.com
newterra ltd.
139