4 Maintenance Procedures
5.
Fit the mounting shaft insertion tool to the mounting shaft.
Notice:
mounting shaft insertion tool to the mounting shaft before fitting
the shaft to the lamp mounting flange.
6.
Slide the lamp mounting flange onto the shaft, taking care to align it
correctly.
7.
Reinsert the shaft through the side of the source enclosure, and fit the
lamp mounting flange to the APPI source enclosure side.
Tighten the securing screws sequentially and by small increments
Tip:
until they are all fully tight. Doing so ensures that the lamp mounting
flange is uniformly seated on the APPI source enclosure side plate.
8.
Use the combined 2.5-mm Allen wrench and cone extraction tool to
tighten the four mounting-flange securing screws.
9.
Remove the mounting shaft insertion tool from the mounting shaft.
10. Fit the PEEK insulator to the end of the mounting shaft.
11. Use the combined 2.5-mm Allen wrench and cone extraction tool to fit
and tighten the two insulator retaining screws.
12. Fit the repeller electrode to the PEEK insulator.
198
March 14, 2014, 715004387 Rev. B
To prevent damage to the mounting shaft O-rings, fit the
Mounting shaft
insertion tool

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents