d) Measure the CKP sensor peak voltage in the
same manner as on the ignitor coupler.
If the peak voltage on the CKP sensor lead wire
couplers is within specification, but on the ignitor
coupler is out of specification, the wire harness
must be replaced. If both peak voltages are out
of specification, the CKP sensor must be
replaced and rechecked.
CKP sensor peak voltage
1.0 V and more (BI – Y)
7) After measuring the CKP sensor peak voltage,
reinstall the removed parts.
CKP Sensor Resistance
1) Remove the left frame cover. Refer to "Exterior Parts
Removal and Installation: in Section 9D".
2) Disconnect the CKP sensor coupler (1).
3) Measure the resistance between the lead wires and
ground. If the resistance is not within the specified
value, the CKP sensor must be replaced. Refer to
"CKP Sensor Removal and Installation: ".
Tester knob indication
Resistance (Ω)
CKP sensor resistance
Approx. 130 – 200 Ω (Blue – Yellow)
∞ Ω (Blue – Ground)
3
2. CKP sensor coupler
4) After measuring the CKP sensor resistance, reinstall
the removed parts.
1
I649G1180014-01
2
Y
Bl
I649G1180015-01
3. CKP sensor
CKP Sensor Removal and Installation
Removal
1) Remove the left frame cover. Refer to "Exterior Parts
Removal and Installation: in Section 9D".
2) Disconnect the CKP sensor coupler (1).
3) Remove the CKP sensor cover.
4) Remove the CKP sensor rotor by removing the bolt.
Ignition System:
1H-8
B649G11806012
1
I649G1180014-01
I649G1180016-01
I649G1180017-01