Installing the MX240 Router By Using a Mechanical Lift

178

Figure 52: Removing an FPC

Because of the router's size and weight—up to 128 lb (58.1 kg) depending on the
configuration—we strongly recommend that you install the router using a mechanical
lift. To make the router light enough to install with a lift, you must first remove most
components from the chassis.
CAUTION:
Before front mounting the router in a rack, have a qualified
technician verify that the rack is strong enough to support the router's weight
and is adequately supported at the installation site.
To install the router using a lift (see
Ensure that the rack is in its permanent location and is secured to the building. Ensure
1.
that the installation site allows adequate clearance for both airflow and maintenance.
Load the router onto the lift, making sure it rests securely on the lift platform.
2.
Using the lift, position the router in front of the rack or cabinet, centering it in front of
3.
the mounting shelf.
Lift the chassis approximately 0.75 in. above the surface of the mounting shelf and
4.
position it as close as possible to the shelf.
Carefully slide the router onto the mounting shelf so that the bottom of the chassis
5.
and the mounting shelf overlap by approximately two inches.
Slide the router onto the mounting shelf until the mounting brackets contact the rack
6.
rails. The shelf ensures that the holes in the mounting brackets of the chassis align
with the holes in the rack rails.
Figure 53 on page
179):
Copyright © 2019, Juniper Networks, Inc.