Access Route and Data Center Room Checklist
TABLE:
Data Center Room Considerations
Yes
No
N/A
Comment
Has the access route been checked for
clearances of the packaged equipment?
Do all the doors and entry ways conform to
the width and height requirements for
transportation, including the width of the
unpacked unit?
Are there any ramps, stairs, or thresholds
that are in the moving path for the new
hardware?
Have you confirmed that the access route is
free of any obstacles that would expose the
device to shock?
If there are stairs, then is a loading elevator
accessible for moving the equipment?
Has the rack location been allocated?
Is there a vacant space in the rack for the
new server?
Does the floor layout meet the equipment
maintenance access requirements?
Is there adequate space available for server
maintenance?
Have cabinet stabilization measures been
considered?
Will the hardware location require any
non-standard cable lengths?
Is the floor to ceiling height a minimum of
2914 mm or 2.9 m (9.6 feet)?
Is the depth of the raised floor a minimum
of 460 mm (18 inches)?
Related Information
"Rack Requirements" on page 40
184
Sun Server X4-2 Installation Guide • February 2014

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Server X4-2 and is the answer not in the manual?

Questions and answers

Table of Contents