iC9200 Series
4.5
Commissioning
4.5.1
Notes on commissioning
HB700 | CPU | PMC921xEx | en | 24-04
2.
On the start bar, click on a project template that corresponds to your firmware
version, such as Yaskawa CPU iC921xM-x
The project template for a blank CPU iC921xM-x opens.
3.
Open 'File Save Project As', assign a meaningful name to your project and close
the dialog with [Save].
WARNING
Prevent automatic start-up
−
Take appropriate measures to ensure that automatic start-up of your plant/
machine is prevented.
NOTICE
Acclimatization before start-up
Make sure that commissioning only takes place after the CPU and the associ-
ated modules have acclimatized!
NOTICE
Damage due to improper handling
−
Handle the CPU and components with care!
−
When installing the CPU and components, ensure that mechanical
damage is avoided!
NOTICE
Startup of the CPU not guaranteed
−
To ensure that the CPU starts up properly, the supply voltage must not be
switched on until at least 30 seconds after the device LEDs go out.
Deployment CPU iC921xM-EC
Commissioning > Notes on commissioning
89