Checklist decommissioning
F
Checklist decommissioning
Checklist
Run.
Requirement
No.
6
Decommissioning
6.1
Is it guaranteed that the decommissioning is done by
authorized and qualified personnel?
6.2
Has the power supply been switched off at the device to
be decommissioned?
6.3
Has the wiring been removed from the device to be
decommissioned?
Has the disassembly been carried out according to the
disassembly description?
⮫ 'Demounting'...page 43
6.4
Is it guaranteed that the defective decommissioned
device is sent to Yaskawa for disposal in its original
packaging?
Date: ......................... Name: ..................... .............. Signature: .................................. ....................