After configuring the master and member switches of the stack with the
previous procedures in this chapter, you are ready to cable the ports of the
stack trunk and power on the stack for the first time. (If you want to monitor
the power-on sequence, connect a terminal or PC with a terminal emulator
program to the Console port on any switch).
To power on the stack for the first time, perform the following procedure:
1. Verify that the master and all member switches are powered off.
2. Cable the ports of the stack trunk on the switches. Refer to Chapter 7,
"Cabling XEM2 Line Card Ports" on page 177.
3. Power on the switches at the same time or within thirty seconds of
each other:
If the switches have AC power supplies, refer to "Powering On
SBxPWRSYS2 AC Power Supplies" on page 154.
If the switches have SBxPWRSYS1-80 DC Power Supplies, power
on the DC circuits and the On/Off switches on the power supplies.
For instructions on wiring the DC connector, refer to Chapter 5,
"Wiring the SBxPWRSYS1-80 DC Power Supply" on page 119.
Refer to "Power Specifications" on page 224 for the power
specifications of the switches.
Warning
Power cord is used as a disconnection device. To de-energize
equipment, disconnect the power cord.  E3
Note
Pluggable Equipment. The socket outlet shall be installed near the
equipment and shall be easily accessible.  E5
4. Wait three minutes for the switches to form the stack.
5. Go to "Verifying the Stack" on page 175.