Please perform the following procedure after installing a chassis:
1. Verify that the chassis has at least one power supply in slot PSU A or
B.
2. If the chassis has only one power supply, verify that the empty power
supply slot on the front panel is covered with a blank panel. For
instructions, refer to "Installing the Blank Power Supply Slot Cover" on
page 115.
3. If the chassis has SBxPWRSYS2 AC Power Supplies, verify that you
installed the power cord retaining clips on the AC power connectors on
the rear panel of the chassis. For instructions, refer to "Installing the
Power Cord Retaining Clips" on page 117.
4. Verify that the grounding lug on the back panel of the chassis is
properly grounded. For instructions, refer to "Installing the Chassis
Grounding Wire" on page 98.
5. Verify that all empty line card slots on the front panel of the chassis are
covered with slot covers. If there are open slots, perform the procedure
"Installing Blank Line Card Slot Covers" on page 113.
If the chassis has SBxPWRSYS1-80 DC Power Supplies, perform the
procedures in Chapter 5, "Wiring the SBxPWRSYS1-80 DC Power
Supply" on page 119.
Repeat the procedures in this chapter to install the other switches of the
stack. Afterwards, go to Chapter 6, "Configuring Switches for Stacking" on
page 149.