Verifying The Installation - Allied Telesis AT-SBx908 Installation Manual

Table of Contents

Advertisement

Chapter 4: Installing the Chassis

Verifying the Installation

108
Please perform the following procedure after installing a chassis:
1. Verify that the chassis has at least one power supply in slot PSU A or
B.
2. If the chassis has only one power supply, verify that the empty power
supply slot on the front panel is covered with a blank panel. For
instructions, refer to "Installing the Blank Power Supply Slot Cover" on
page 105.
3. If the chassis has AT-SBxPWRSYS2 AC Power Supplies, verify that
you installed the power cord retaining clips on the AC power
connectors on the rear panel of the chassis. For instructions, refer to
"Installing the Power Cord Retaining Clips" on page 107.
4. Verify that the grounding lug on the back panel of the chassis is
properly grounded. For instructions, refer to "Installing the Chassis
Grounding Wire" on page 88.
5. Verify that all empty line card slots on the front panel of the chassis are
covered with slot covers. If there are open slots, perform the procedure
"Installing Blank Line Card Slot Covers" on page 103.
If the chassis has AT-SBxPWRSYS1-80 DC Power Supplies, perform the
procedures in Chapter 5, "Wiring the AT-SBxPWRSYS1-80 DC Power
Supply" on page 109.
Repeat the procedures in this chapter to install the other switches of the
stack. Afterwards, go to Chapter 6, "Configuring Switches for Stacking" on
page 139.