Testing Power Converter Voltages Sms - Nortel DMS-100 Series Maintenance Manual

Subscriber carrier module-100s
Hide thumbs Also See for DMS-100 Series:
Table of Contents

Advertisement

Application
Use this procedure to test power converter voltages for all power converters
in the subscriber carrier equipment (SME) frame.
Interval
Perform this procedure every six months.
Common procedures
There are no common procedures
Action
This procedure contains a summary flowchart and a list of steps. Use the
flowchart to review the procedure. Follow the steps to perform the
procedure.
12-17
Routine maintenance procedures
Testing power converter voltages
Testing power converter voltages
DMS-100 Family SMS Maintenance Manual XPM10 and up
12-17
12-17
SMS
SMS