After configuring a member switch, do the following:
1. Power off the switch by performing the following:
For the DC power supply, power off the DC power source units.
For the AC power supply, disconnect the AC power cords from the
AC power sources. Refer to Figure 125 on page 208.
2. Repeat the procedures in this chapter to configure any additional
member switches.
3. If you have not already configured the master switch, perform
"Configuring the Master Switch - Part I" on page 200.
4. After configuring the master and member switches, verify that all the
units are powered off.
5. Cable the stacking ports on the master and member switches. Refer to
Chapter 13, "Cabling the Networking Ports" on page 225.
6. Power on the switches of the stack, as explained in "Powering on the
Stack" on page 222.
7. Verify that the switches have successfully formed the stack by
performing "Verifying the Stack" on page 223.
8. Cable the networking ports, as explained in Chapter 13, "Cabling the
Networking Ports" on page 225.