What To Do Next - Allied Telesis AT-SBx908 Installation Manual

Table of Contents

Advertisement

Step
4
Enter the SHOW RUNNING-CONFIG command to display the running configuration
of the master switch:
awplus# show running-config
Use the display to confirm that you designated the correct trunk ports for the master
and member switches. The ports should be designated with INTERFACE PORT and
STACKPORT commands. In the following example, the stack trunk will consist of
ports 1 to 4 on the line cards in slot 4 on the master (port1) and member switches:
interface port1.4.1-1.4.4
stackport
.
interface port2.4.1-2.4.4
stackport
.
interface port3.4.1-3.4.4
stackport
.
interface port4.4.1-4.4.4
stackport
Go to "What to Do Next" on page 155.
5

What to Do Next

Table 15. Verifying the Master Switch (Continued)
Description and Command
After configuring the master switch, do the following:
1. Power off the switch, as follows:
For AC power supplies, disconnect the AC power cords from the
AC power sources.
For AT-SBxPWRSYS1-80 DC Power Supplies, power off the On/
Off switch on the power supplies. Refer to Figure 60 on page 111.
2. Configure the member switches. Refer to "Configuring Member
Switches" on page 156.
3. After configuring the master and member switches, cable the ports of
the stack trunk. Refer to Chapter 7, "Cabling AT-XEM2 Line Card
Ports" on page 167.
4. Power on the master and member switches of the stack. Refer to
"Powering on the Stack" on page 164.
5. Verify the stack by referring to "Verifying the Stack" on page 165.
6. Cable the networking ports. Refer to Chapter 7, "Cabling AT-XEM2
Line Card Ports" on page 167.
AT-SBx908 GEN2 Installation Guide for Virtual Chassis Stacking
155

Advertisement

Table of Contents
loading

Table of Contents