12. Install the drive cage.
13. Observe the guidelines for managing cables.
14. Connect the drive SATA-power split cable to the drives and system board.
15. If the fan cage was removed, do the following:
a. Make sure that all the system cables that are routed through the front cable channel are properly
secured in the metal cable tabs. This is done to prevent system damage due to cables being
inadvertently caught under the fan cage.
b. Install the fan cage on page 55
16. Install the air baffle on page 51.
17. Install the access panel on page 49.
18. Do one of the following:
Server in tower mode: Position the tower server for operation on page 42.
Server in rack mode: Slide the server into the rack on page 47.
19. Connect all peripheral cables to the server.
20. Connect each power cord to the server.
21. Connect each power cord to the power source.
22. Power up the server on page 38.
23. Install the front bezel on page 40.
The installation is complete.
To configure arrays, see the HPE Smart Array SR Gen10 Configuration Guide at the Hewlett Packard
Enterprise website.

Installing an LFF hot-plug drive

CAUTION:
To prevent improper cooling and thermal damage, do not operate the server unless all bays are
populated with either a component or a blank.
Prerequisites
Before you perform this procedure:
66
Installing an LFF hot-plug drive