Quantum scalar i2000 User Manual page 290

Hide thumbs Also See for scalar i2000:
Table of Contents

Advertisement

Scalar i2000 User's Guide
Test Descriptions
This section describes the verification tests that are available.
Installation Verification Test
The installation verification test enables you to verify that the library's
installation and configuration is complete and functioning correctly. The
installation verification test runs the following individual tests:
Library alignment test
Picker assembly test
I/E station assembly test
Get/put test
Scanner fiducial test
The smaller library configuration will require about 1 hour and the larger
configurations will require as long as 4 hours to run the installation
verification test. The time to complete individual tests on an eight-frame
configuration is approximately:
Library alignment test - 30 minutes
Picker assembly test - 1 minute
I/E station assembly test - 5 minutes for each I/E station
Get/put test - 120 minutes
Scanner fiducial test - 75 minutes
These times do not include debug or repair time.
Note
Partial System Tests
The partial system tests perform the selected subtests to test an area or
range of the library configuration. The selectable tests include:
• Frame test - This test includes the same individual tests as the
installation verification test, but enables you to specify a range of
modules rather than testing all modules.
• Configuration test - This test includes the picker assembly and
scanner fiducial tests.
Chapter 5 Maintaining Your Library
Maintenance Actions
5
5
5
277

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the scalar i2000 and is the answer not in the manual?

Table of Contents