C1009X4C
Explanation: Processor wire test IPL step in progress
Response:
1. Search RETAIN tips and the firmware change history for the reference code to determine the recommended
actions. If a firmware update is needed, see Updating the firmware.
2. Replace the system-board, as described in Replacing the system-board and chassis assembly.
C1009X50
Explanation: Processor long scan IPL step in progress
Response:
1. Search RETAIN tips and the firmware change history for the reference code to determine the recommended
actions. If a firmware update is needed, see Updating the firmware.
2. Replace the system-board, as described in Replacing the system-board and chassis assembly.
C1009X54
Explanation: Start processor clocks IPL step in progress
Response:
1. Search RETAIN tips and the firmware change history for the reference code to determine the recommended
actions. If a firmware update is needed, see Updating the firmware.
2. Replace the system-board, as described in Replacing the system-board and chassis assembly.
C1009X58
Explanation: Processor SCOM initialization step in progress
Response:
1. Search RETAIN tips and the firmware change history for the reference code to determine the recommended
actions. If a firmware update is needed, see Updating the firmware.
2. Replace the system-board, as described in Replacing the system-board and chassis assembly.
C1009X5C
Explanation: Processor interface alignment procedure in progress
Response:
1. Search RETAIN tips and the firmware change history for the reference code to determine the recommended
actions. If a firmware update is needed, see Updating the firmware.
2. Replace the system-board, as described in Replacing the system-board and chassis assembly.
C1009X4C • C1009X5C