8.3
Commissioning using the AOP30 operator panel
8.3.1
First commissioning
Note
To operate the AOP30, p2030=3 must be set.
8.3.1.1
First power-up
Start screen
When the system is switched on for the first time, the Control Unit (CUD) is initialized
automatically. The following screen is displayed:
Figure 8-2
While the system is powering up, the parameter descriptions are loaded to the operator
panel (remark: The Memory Card does not have to be inserted)
Figure 8-3
SINAMICS DCM DC Converter
Operating Instructions, 1.2012, C98130-A7066-A1-05-7619
Splash screen
0%
50%
Loading the parameter descriptions while powering up the system
8.3 Commissioning using the AOP30 operator panel
100%
Commissioning
231