5.3

Commissioning using a BOP-2 operator panel

Plugging on an operator panel
Procedure
To plug an Operator Panel on the Control Unit, proceed as follows:
1. Locate the lower edge of the Operator Panel into the matching recess
of the Control Unit.
2. Press the Operator Panel onto the inverter until you hear the latching
mechanism engage.
You have plugged an operator panel onto the Control Unit.
The operator panel is ready for operation when you connect the inverter to the power supply.
5.3.1

Starting basic commissioning

Carry out basic commissioning
Preconditions
Converter with CU230P-2 Control Units
Operating Instructions, 04/2015, FW V4.7 SP3, A5E34257946B AB
5.3 Commissioning using a BOP-2 operator panel
• The power supply is switched on.
• The operator panel displays setpoints and actual values.
Commissioning