Put back all 4 bolts in their respective holes before tightening them up.
Unfold both follower panels.
10 g.
All panel rollers must now rest on the lower section of both side rails.
11.
Reinstall the upper part of both side rails (one on each side of the hopper).
12.
Reinstall the transversal beam and its retaining bolts (2 on each side).
13.
Put back the deflector panel (see Figure 3-260).
14.
Reinstall both anti-spill guards.
15.
Start the engine and engage the hydraulic pump.
16.
Run a full cycle to check for proper operation.
Danger!
Do not enter the hopper while the packer is moving.
B. Standard and Co-Mingle Units W/O Loading Arm
To replace the panel roller assemblies:
N
: This task must be performed by 2 people.
OTE
1.
Start the engine and engage the hydraulic pump.
2.
Fully retract the packer.
Danger!
Do not enter the hopper while the packer is moving.
3.
Co-mingle units only: Set the chute upright.
4.
Turn OFF the hydraulic pump and the engine.
5.
Lock out and tag out the vehicle (see Locking Out and Tagging Out the Vehicle on page 14).
6.
Open the left/right hand side hopper door.
7.
Remove the anti-spill guards located on each side of the hopper (see Figure 3-258).
An R-pin located just behind the anti-spill guard (see Figure 3-259) must be pulled completely to
allow for the removal of the guard.
8.
Open both floating panels (see Step 6 on page 168).
9.
Remove the left-hand side bottom roller and replace it. To do so:
Using a 5⁄16-inch Allen wrench and a 3⁄4-inch box, remove all 4 bolts that keep the roller in
9 a.
place (see Figure 3-264).
Remove the panel roller and replace it with a new one.
9 b.
Put back all 4 bolts in their respective holes before tightening them up.
9 c.
General Maintenance 183