10.
Install the new sliding shoes on the floor guides.
11.
Weld a temporary tube on both floor guides.
Both tubes must be positioned about six inches from the body end of the floor guides. This is
done to facilitate the insertion of the sliding shoes under the packer.
12.
Exit the hopper.
13.
Start the truck and engage the hydraulic pump.
14.
Slowly extend the packer to make the sliding shoes go under it.
Danger!
Never enter the hopper while the packer is moving.
15.
When the sliding shoes are back in place, turn OFF the hydraulic pump and the engine.
16.
Lock out and tag out the vehicle (see Locking Out and Tagging Out the Vehicle on page 14).
17.
Put back and tighten all retaining bolts.
18.
Remove the tubes that were installed in Step 11, then grind down to a smooth surface.
: If the wear pads at the top of the packer need to be replaced, see Upper Wear Pads on page 135.
N
OTE
19.
Start the truck and engage the hydraulic pump.
20.
Extend the packer.
21.
Turn OFF the hydraulic pump and the engine.
22.
Lock out and tag out the vehicle (see Locking Out and Tagging Out the Vehicle on page 14).
23.
Align the packer with the hopper walls.
24.
Tack weld both floor guides to the floor.
Figure 3-176
Tack weld on both sides of the floor guide
25.
Start the truck and engage the hydraulic pump.