Commissioning (software)
7.1 Overview of commissioning
7.1.3

Important functions for the project handling during commissioning

The following functions are very important for the project handling and commissioning:
Table 7-2
Symbol
Note
Tips for going ONLINE:
In online operation, SCOUT attempts to conduct online operation with all hardware
components contained in the project. This means that the time needed for going online
increases.
We recommend that you make settings for SCOUT so that online operation is made only with
those components currently needed. The setting can be found at "Target system > Select
target devices..." in the menu. The selection and deselection of the devices in the online state
can be made via the "Connect target device" context menu on the device.
This procedure is also advantageous when the configuration of the drive unit is completed.
Without going completely offline, the connection can be simply deselected via the context menu
on the drive unit.
174
Buttons for operator control
Function
Effect
Save project
Select Save project and compile changes to save the entire project
and compile
and compile the project data (e.g. programs) in an executable code.
changes
Only the changes are compiled. Unchanged code is retained.
Connect to se‐
The online connection is established to the selected target devices.
lected target de‐
Under "Target system" > "Select target devices", you can set which
vices
target devices are to go online.
Download
Downloading programs to the SIMOTION device and performing
project to target
configuration for the SINAMICS Integrated and any connected
system
CX32‑2 modules.
Download CPU /
The configuration is only loaded to the device selected in the project
drive unit to tar‐
tree (which means that the function needs to be performed sepa‐
get device
rately for each D4x5‑2/CX32‑2 and each SINAMICS Integrated).
Load CPU /
The unit's configuration is only loaded to the PG selected in the
drive unit to PG
project tree (which means that the function needs to be performed
separately for each D4x5‑2/CX32‑2 and each SINAMICS Integra‐
ted).
Copy RAM to
Copying from RAM to ROM is only performed for the device selected
ROM
in the project tree (which means that the function needs to be per‐
formed separately for each D4x5‑2/CX32‑2 and each SINAMICS
Integrated).
Commissioning and Hardware Installation Manual, 03/2018, A5E33441636B
SIMOTION D4x5-2

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Simotion cx32-2Simotion cbe30-2Simotion tb30

Table of Contents