Commissioning (hardware)
5.1 Requirements for commissioning
To load the SIMOTION Kernel, the CF card must be inserted when the SIMOTION D4x5‑2 is
powered up.
NOTICE
Damage to the CompactFlash card from electrical fields or electrostatic discharge
The CompactFlash card is an ESD-sensitive component.
De-energize the SIMOTION D4x5‑2 device before inserting or removing the CompactFlash
card. The SIMOTION D4x5‑2 is in a de-energized state when all the LEDs are off.
Comply with the ESD rules.
96
Commissioning and Hardware Installation Manual, 03/2018, A5E33441636B