Shield connection for TB30
The following figure shows the cable routing, cable connection and the connection of the I/Os
on the TB30. The TB30 is inserted in a CU320-2 here.
Figure 4-10
Shield connection for TB30 using the digital I/Os as an example
The arrangement is similar when inserted in a D4x5-2, see also Section Creating a shield
connection (Page 72) for more details.
The permissible bending radii for the cables must be maintained when the cables are being
laid.
SIMOTION D4x5-2
Commissioning and Hardware Installation Manual, 03/2018, A5E33441636B
Connecting
4.6 Connecting I/Os
75