Supplementary conditions
This manual assumes the following general conditions:
● The mechanical and electrical installation of the system must have been completed.
● Check the system visually for:
– Correct mechanical installation with secure electrical connections
– Connection of the power supply
– Connection of the shielding and grounding
● Switching on the control and startup in "Normal startup":
The control has finished booting when the main screen of the operating software is
displayed.
References
The commissioning of the technology cycles can be found in the SINUMERIK Operate
(828D_IH9) Commissioning Manual, in Section "Configuring cycles".
CNC commissioning
Commissioning Manual, 10/2015, 6FC5397-3DP40-5BA3
Scope of delivery and requirements
1.3 Commissioning process