18 - Test

Presentation All the trip units of the Ekip Touch range allow you to carry out various checks directly from the display:
Autotest The automatic sequence of the display and the LED is activated by selecting the command Autotest.
Trip Test Selecting the command Trip test opens a dedicated page that asks you to confirm running the test by
118 | © 2017 ABB | 1SDH001330R0002 - ECN000058721 Rev. A
Path Main page - Menu - Test
• Autotest, for the check on the display and the LEDs.
• Trip Test, for the check on the circuit breaker opening command.
• Test CB, for the check on the controls of the circuit-breaker opening and closing coils
• Zone Selectivity, for the check on Zone Selectivity inputs and outputs.
In the presence of auxiliary power supply and contact type modules, the dedicated sections are enabled:
• Ekip Signalling 4K allows the check of LED and contacts of the module.
• Ekip Signalling 2K-1, 2K-2, 2K-3 allows the check of LED and contacts of the module.
• Ekip Signalling 10K-1, 10K-2, 10K-3 allows LEDs to be checked and contact closing commands to
be sent.
In the presence of an Rc type trip unit and auxiliary power supply, the dedicated test section is enabled:
• Rc Test allows you to check connection and proper operation of the toroid Rc
NOTE: access to the Test Menu requires the insertion of the password.
Using the Ekip T&P and Ekip Bluetooth test accessories it is also possible to check the operation of the
electronic protections from a PC, by simulating various installation conditions.
The sequence includes the following test phases:
Phase
Operation
1
Screen with message "www.abb.com"
2
Darkening of the display
3
Color sequence with red, green, blue bands, with gradual increase of backlighting
4
Warning and Alarm LEDs switched on for 1 second
pressing the iTest key for at least 7 seconds.
When the key is pressed, an opening command is sent to the trip coil.
IMPORTANT: the opening command is performed with circuit-breaker closed and
absence of circulating currents.
Test CB Selecting the command Test CB opens a submenu containing the commands Open CB and Close CB.
The commands allow you to activate coil opening and closing respectively: the correct sending of the
command is confirmed by a window with the message "Test Executed".
The correct operation of the entire command system (trip unit, Ekip Com Actuator and opening and closing
coils) is verified through the opening and/or the closing of the circuit-breaker.
ABB | SACE Emax 2
Continued on the next page
Ekip Touch protection trip unit | 18 - Test

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sace emax e2.2Sace emax e4.2Sace emax e6.2

Table of Contents