Selectivity Between Abb Sace Circuit-Breakers; Foreword; Types Of Selectivity; Further Documents - ABB SACE Emax E1.2 Operating Instructions For The Design Engineer

Sace emax 2 series low voltage air circuit-breakers
Hide thumbs Also See for SACE Emax E1.2:
Table of Contents

Advertisement

2 - Selectivity between ABB SACE circuit-breakers

Foreword It is possible to obtain selectivity between ABB SACE circuit-breakers (including Emax 2).
Types of selectivity With ABB SACE electronic trip units selectivity can be:
Further documents For each type of selectivity, the protections must be set so that only those circuit-breakers capable of isolating
9 | © 2017 ABB | 1SDH001330R0002 - ECN000058721 Rev. A
There is selectivity in an installation when, in the event of an overload or short-circuit, it is possible to identify
and isolate the point of overload or fault by opening only some circuit-breakers to guarantee service continuity
to the installation.
NOTE: selectivity is recommended in all installations with multiple switchgears or circuit-
breakers connected, for example cascading or in a tree (with a main circuit-breaker on the
supply side, and other circuit-breakers downstream to protect areas on the other side). Thus,
only the circuit-breaker immediately upstream the overload or fault trips, and avoids opening
of the circuit-breakers further upstream.
• Current-based selectivity, activated in the event of over-current, and in which the protections of the
trip units are set with different current thresholds, based on the principle the closer the fault point is to the
power supply the greater the current will be.
• Time selectivity, activated in the event of a short-circuit in which the S protection normally trips, and in
which the protections of the trip units are set with different tripping times, so that with cascading circuit-
breakers the circuit-breakers further downstream open before those further upstream.
• Time-current selectivity, which is a combination of the previously mentioned types, and in which the
protections of the trip units are set so that the tripping times and current thresholds increase with proximity
to the power supply.
• Energy selectivity, which uses current-limiting circuit-breakers, characterized by extremely short tripping
times in the event of a short-circuit to avoid the current reaching the peak value (in the case of ABB SACE
circuit-breakers, for example, all the moulded-case circuit-breakers of the Tmax series and certain air
circuit-breakers of the Emax series are limiters).
• Zone Selectivity, which is an evolution of time selectivity, and in which is a dialog created between the
trip units by means of output and input blocking signals. For more information on Zone Selectivity with
ABB SACE circuit-breakers and in particular Emax 2, see the chapter "Specific applications" starting on
page 156.
the overload or fault open, without the rest of the installation being de-energized. Relevant definitions, operating
principles, areas of application, advantages and disadvantages, requirements, indications for setting the
protections and examples are provided in the Technical Application Paper QT1
voltage selectivity with ABB circuit-breakers".
1SDC007100G0205
Guide to the product choice | 2 - Selectivity between ABB SACE circuit-breakers
ABB | SACE Emax 2
"Low

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sace emax e2.2Sace emax e4.2Sace emax e6.2

Table of Contents