Zero Point Adjustment wizard (menu item 1.2)
The flowmeter system is optimized through an automatic zero point adjustment. Before you
start the zero point adjustment flush the pipe and keep it filled at an absolute flowrate of zero.
Ensure that the sensor has the same temperature as the process media. Perform at operating
pressure or at least 0.2 barg.